While the structural steel is being fabricated by VanDellen Steel, it is being erected by their partner, G2 Erectors. Following the detailed shop drawings provided by VanDellen and approved by the structural engineer, G2 is nearly complete with erecting all the structural steel. Part of this process includes welding down hundreds of “studs” onto the 3rd and 2nd floor metal decking. These studs, along with welded wire fabric, provide crucial support for the concrete that will be placed on the decking in the coming weeks - this system is known as a composite concrete floor slab. The finishing touches for the structural steel will be complete the first week of March, with steel stud framing and pouring of the concrete slabs following immediately after.